Police station taking shape on schedule

By Martin B. Cassidy
Staff Writer

June 6, 2007

Steel girders appeared on Havemeyer Place this week as the framework of the town's new police station begins to rise, and town officials said construction of a new public safety complex is on schedule.

"It's on time and there haven't been any unforeseen costs during construction," town Superintendent of Building Construction and Maintenance Alan Monelli said.

Bethel-based Worth Construction will finish the steel frame of the police station by July, Monelli said, before erecting a 177-space parking garage on the site for public safety personnel over six weeks between Labor Day and October, Monelli said.

The loss of parking due to the construction prompted the town to assign police officers to park at Town Hall, to save parking for shoppers.

"We're trying to get the garage open as quickly as possible," Monelli said. "But in terms of sequencing the building is going up right now."

Worth Construction began construction on the $32 million police station in February, part of a three phase project to gather police, fire, and emergency medical operations under one roof.

Since last fall, the entire police department has been relocated across the street to the Police/Fire Building, until the police department is finished sometime in 2009.

The complex will include a glass-and-metal public atrium and a second-story footbridge linking a parking garage to the renovated central fire station.

First Selectman Jim Lash said that URS Corp., the company hired to oversee the construction makes a comprehensive report on progress and any delays in the project regularly.

Earlier this year the town ended up spending more than twice what had been planned to excavate the site, after finding that contamination of soil on the site was greater than thought, Lash said.

After awarding A. Vitti Excavators a $1.2 million contract to excavate the site, the cost of moving 16,000 tons of contaminated soil to a landfill brought the cost of the excavation to nearly $2.9 million, according to town documents.

The contamination was linked to a Nash car dealership that occupied the site before the police administration building was built in the 1950s and gasoline tanks that were once used to fuel police cars.

"We spent more of the contingency on soil removal then we had hoped," Lash said. "But the construction is going fine."

Board of Estimate and Taxation Chairman Peter Tesei said that construction projects often entail unexpected cost increases due to the cost of materials or other obstacles.

Tesei said Lash updates the finance board on the project's progress periodically.

"Constructing a new building is a far greater task with a larger scope of work involved," Tesei said.

The last phase of the project will be to renovate the 69-year-old Police/Fire Building into a fire house sometime beginning in 2010.

Copyright © 2007, Southern Connecticut Newspapers, Inc.